Major Projects - First Stage of Site Formation and Engineering Infrastructure at Kwu Tung North and Fanling North New Development Area
First Stage of Site Formation and Engineering Infrastructure at Kwu Tung North and Fanling North New Development Area
Project Number:
7759CL
Brief Description of Project Scope:
The Project is part of the first phase of the Kwu Tung North (KTN) and Fanling North (FLN) New Development Area (NDA) development and comprises mainly :
development of a nature park at Long Valley of about 37 hectares (ha) including provision of a visitor centre and a footbridge of about 50 metres long spanning across Sheung Yue River for connection between the nature park and the visitor centre;
reprovisioning of two egretry sites in the FLN NDA and enhancement works to an existing egretry site in the KTN NDA;
site formation of about 2.3 ha of land (including soil treatment works) for a village resite area and a district police station in the KTN NDA;
engineering infrastructure works including roads, drainage, sewerage, waterworks, slopeworks and landscaping works; and
implementation of environmental mitigation measures and environmental monitoring and audit (EM&A) programme for the works mentioned in items (a) to (d) above.
Project Office in Civil Engineering and Development Department:
North Development Office (Enquiry: 3422 3381)
Consultant:
AECOM Asia Company Limited
Approved Project Estimate:
$896.4 million
Related Website:
http://ktnfln-ndas.gov.hk/en/index.php
Current Progress:
Construction commenced in December 2019
Contractor:
Contract No. ND/2019/03
Scope:
The contract mainly comprises development of a nature park at Long Valley and ecological mitigation and enhancement works for the nature park.
Commencement Date:
19 December 2019
Completion Date:
28 March 2024 (Actual Completion)
Contract Sum:
$430 Millions
Contractor:
Sang Hing - Kuly Joint Venture
Contract No. ND/2019/02
Scope:
The contract mainly comprises road and drainage works between Kwu Tung North New Development Area and Shek Wu Hui; construction of a sewage pumping station, a Long Valley Nature Centre and a footbridge spanning across Sheung Yue River; and site formation of land and the associated engineering infrastructure works for a village resite area in Kwu Tung North New Development Area.
Commencement Date:
17 February 2020
Completion Date:
2026
Contract Sum:
$1040 Millions
Contractor:
Chun Wo - Kwan Lee Joint Venture