Major Projects - Remaining Phase of Site Formation and Engineering Infrastructure Works at Kwu Tung North and Fanling North New Development Area - Detailed Design and Site Investigation
Remaining Phase of Site Formation and Engineering Infrastructure Works at Kwu Tung North and Fanling North New Development Area - Detailed Design and Site Investigation
Project Number:
7828CL
Brief Description of Project Scope:
The Remaining Phase Works mainly cover –
(a) site formation of about 247 hectares of land (including soil treatment works) in the Kwu Tung North (KTN) and Fanling North (FLN) New Development Area (NDA) for housing, community, commercial and other developments as well as engineering infrastructure works;
(b) engineering infrastructure works including Fanling Bypass (Western Section), Po Shek Wu Road Flyover, new interchanges together with widening of Fanling Highway for connection with KTN NDA, local roads, cycle tracks, drainage, sewerage, waterworks, pumping stations, fresh water and flushing water service reservoirs, and landscaping works; and
(c) implementing the environmental mitigation measures for the works mentioned in (a) to (b) above.
Project Office in Civil Engineering and Development Department:
North Development Office (Enquiry: 3547 1624)
Consultant:
Agreement No. CE 18/2019 (CE) - “Development of Fanling North New Development Area, Remaining Phase – Design and Construction”
- Atkins China Limited
Agreement No. CE 19/2019 (CE) - “Development of Kwu Tung North New Development Area, Remaining Phase – Design and Construction”
- AECOM Asia Company Limited
Agreement No. CE 20/2019 (HY) - “Improvement of Tai Tau Leng Roundabout and Fanling Highway (Kwu Tung Section) - Design and Construction”
- AECOM Asia Company Limited
Agreement No. CE 21/2019 (WS) - “Fresh Water and Flushing Water Service Reservoirs and Associated Works in Fanling North – Design and Construction”
- Black & Veatch Hong Kong Limited
Approved Project Estimate:
$30,167.9 million
Related Website:
https://www.ktnfln-ndas.gov.hk/en/
Current Progress:
Construction commenced in July 2024.
Contract:
Contract No. ND/2024/01 - Kwu Tung North New Development Area, Remaining Phase: Site Formation and Infrastructure Works (South)
Scope:
The works mainly comprise site formation of lands (including site clearance and land decontamination works) and ground investigation within Kwu Tung North New Development Area (KTN NDA); construction of at-grade roads within KTN NDA connecting to Castle Peak Road (Kwu Tung Section) and Fanling Highway; construction of a vehicular bridge connecting proposed Road L1 and Road L2; construction of footbridges at proposed Road P2; construction of noise barriers and low noise road surfacing; construction of common utility enclosure and associated works; construction of a visitor centre; and ancillary works including footpaths, cycle tracks, lighting, traffic aids, drainage, sewerage, water mains, district cooling mains, landscaping works, slope works and electrical and mechanical works.
Commencement Date:
23 August 2024
Completion Date:
2030
Contract Sum:
$4,107 million
Contractor:
Build King – Richwell Engineering Joint Venture
Contract No. ND/2024/02 - Kwu Tung North New Development Area, Remaining Phase: Site Formation and Infrastructure Works (North)
Scope:
The works mainly include site formation of lands (including site clearance and land decontamination works) and ground investigation within Kwu Tung North New Development Area (KTN NDA); construction of at-grade roads within KTN NDA; construction of noise barriers and low noise road surfacing; and ancillary works including footpaths, cycle tracks, lighting, traffic aids, drainage, sewerage, water mains, district cooling mains, landscaping works, slope works, flood prevention works and electrical and mechanical works.
Commencement Date:
16 December 2025
Completion Date:
2031
Contract Sum:
$1,277 million
Contractor:
Build King – Richwell Civil Joint Venture
Contract No.
ND/2024/