Major Projects - Tung Chung New Town Extension
Tung Chung New Town Extension
Project Number:
7786CL
Brief Description of Project Scope:
The project is to further develop the Tung Chung New Town (TCNT) into a comprehensively planned new town with a larger population capacity and adequate local and regional community facilities. The project comprises mainly:
Reclamation works for about 130 hectares (ha) of land including construction of associated seawall and eco-shoreline for the development of Tung Chung New Town Extension (TCNTE) at Tung Chung East and a primary distributor road (Road P1);
Site formation works for about 7 ha of land for the development of TCNTE at Tung Chung West;
Engineering infrastructure works including roads, footbridges, drainage, sewerage, waterworks, sewage and salt water pumping stations, fresh water and salt water service reservoirs, and flood protection measures;
Provision of new cycle tracks connection to the existing cycle track network;
Revitalization of the channelized portion of Tung Chung Stream and provision of a river park;
Landscaping, reprovisioning and ancillary works; and
Environmental mitigation measures including noise barriers for the works mentioned in (i) to (vi) above.
Project Office in Civil Engineering and Development Department:
South Development and Sustainable Lantau Office (Enquiry: 2231 4408)
Consultant:
Agreement No. CE 69/2015 (CE) – “Tung Chung New Town Extension (East) – Design and Construction”
- AECOM Asia Company Limited
Agreement No. CE 70/2015 (CE) – “Tung Chung New Town Extension (West) – Design and Construction”
- Ove Arup & Partners Hong Kong Limited
Agreement No. 9AJ126 - "Open Space Development in Tung Chung New Town Extension (East) – Design and Construction"
- P&T Architects Limited
Agreement No. 9QK102 - "Quantity Surveying Services for Open Space Development in Tung Chung New Town Extension (East)"
- Arcadis Hong Kong Limited
Related Website:
www.tung-chung.hk
Current Progress:
The detailed design of site formation and infrastructure works under TCNTE development commenced in 2016 in phases for target completion of works in 2030. Reclamation works (Contract No. NL/2017/03) were substantially completed in January 2023. Salt Water Supply System (Contract No. NL/2020/02), Major Infrastructure Works in Tung Chung East (Contract No. NL/2020/03), Siu Ho Wan Fresh Water Service Reservoir and Associated Mainlaying Works (Contract No. NL/2020/04), Site Formation and Infrastructure Works at Ma Wan Chung (Contract No. NL/2020/05), Site Formation and Infrastructure Works at Tung Chung Valley, Phase 1 (Contract No. NL/2020/06), Tai Ho Interchange (Contract No. NL/2020/07), Infrastructure Works at Tung Chung Valley, Yu Tung Road and Ma Wan Chung (Contract No. NL/2023/10), Infrastructure Works at Tung Chung Valley, Phase 2 (Contract No. NL/2023/11), Open Space Development in TCNTE (East), Phase 1 (Contract No. NL/2023/13) and
Infrastructure Works at Ying Hei Road and Tung Chung Waterfront Road (Contract No. NL/2025/09)
are in progress.
Contract:
Contract No. NL/2017/03
Scope:
The contract mainly comprises reclamation of the seabed at Tung Chung East by non-dredging methods to form a total of about 130 hectares of land; construction of seawalls with eco-shorelines; construction of a multi-cell drainage box culvert; provision of infrastructure for Tung Chung Area 58; and implementation of the associated environmental mitigation measures.
Commencement Date:
29 December 2017
Completion Date:
10 January 2023
Awarded Sum:
$12,076 million
Contractor:
Build King-SCT Joint Venture
Contract No. NL/2020/02
Scope:
The contract mainly comprises construction of Tung Chung Salt Water Pumping Station and Salt Water Service Reservoir, laying of salt watermains and fresh watermains and compensatory woodland planting.
Commencement Date:
21 June 2021
Completion Date:
2026
Awarded Sum:
$351 million
Contractor:
China Geo-Engineering Corporation
Contract No. NL/2020/03
Scope:
The contract mai