Major Projects - Site Formation and Infrastructure Works for the Development of ex-Cha Kwo Ling Kaolin Mine Site (Phase 2)
Site Formation and Infrastructure Works for the Development of ex-Cha Kwo Ling Kaolin Mine Site (Phase 2)
Project Number:
7771CL
Brief Description of Project Scope:
The works mainly comprise:
(a) site clearance and formation, as well as construction of related retaining walls and slopes;
(b) construction of a carriageway with associated footpaths to connect Ko Ling Road and the development of ex-Cha Kwo Ling Kaolin Mine Site (Phase 2), and associated improvement works for nearby roads; and
(c) associated ancillary works including drainage works, sewerage works, waterworks and roadside greening works.
Project Office in Civil Engineering and Development Department:
South Development and Sustainable Lantau Office
Consultant:
AECOM Asia Co. Ltd.
Approved Project Estimate:
$675.6 million
Current Progress:
Construction commenced in July 2023.
Contract:
Contract No.
SD/2022/02
Scope
Same as project scope above plus the advance works for the Project of Site Formation and Infrastructure Works for Public Housing Development at Cha Kwo Ling Village, Kowloon East
Commencement Date
31 July 2023
Completion Date
2027
Contract Sum
Around $680 million
Contractor:
Vibro Joint Venture (SD/2022/02)
Other Related Information:
Gazette Date
Subject
4 September 2015 & 11 September 2015
Authorization of Scheme
G.N. 6604
29 May 2015 & 5 June 2015
Scheme
G.N.3657
Scheme
Plan(s)
GAZ/201
GAZ/202
GAZ/203