Major Projects - Site Formation and Infrastructure Works for Public Housing Development at Shap Pat Heung, Yuen Long
Site Formation and Infrastructure Works for Public Housing Development at Shap Pat Heung, Yuen Long
Project Number:
B874CL
Brief Description of Project Scope:
Project scope comprises:
(i) site formation works including site clearance and land decontamination works, if required;
(ii) geotechnical works including slope works and construction of retaining structures, if required;
(iii) roadworks;
(iv) sewerage and drainage works;
(v) associated tree felling, transplanting and preservation works; and
(vi) ancillary works including waterworks, landscaping works, environmental mitigation measures, etc.
Project Office in Civil Engineering and Development Department:
Housing Projects Unit, Civil Engineering Office
Consultant:
Binnies Hong Kong Limited
Current Progress:
Investigation and design works commenced in July 2022.
Other Related Information:
Gazette Date
Subject
13 October 2023
&
20 October 2023
Authorization
G.N. 6142
G.N. 6143
30 June 2023
&
7 July 2023
Works Scheme
G.N. 3804
Scheme
Plan(s)
4110336/BIN/S&T/GZ/001
YLM11055
G.N. 3805
Scheme
Plan(s)
4110336/BIN/S&T/GZ/006