Major Projects - San Tin Technopole Phase 1 Stage 1 Works - Site Formation and Engineering Infrastructure
San Tin Technopole Phase 1 Stage 1 Works - Site Formation and Engineering Infrastructure
Project Number:
7899CL
Brief Description of Project Scope:
site clearance and formation (including geotechnical works and land decontamination works) for about 158 hectares ("ha") of land, to supply land for development of innovation and technology ("I&T") uses, logistics, housing, Government, Institute or Community ("GIC") facilities, open spaces, etc., and for construction of the road and infrastructure works in sub-paragraphs (b) and (c) below;
upgrading of a section of San Tin Highway of about 2 kilometres ("km"), construction of associated district distributors and local roads of about 8 km long in total, cycle tracks of about 8.5 km long and footpaths, and associated junction/road improvements;
construction of other engineering infrastructure works including drainage system, sewerage system (including two sewage pumping stations); water supply systems (including a fresh water service reservoir and a reclaimed water service reservoir with capacity of about 132 000 cubic metres ("m3 ") and 31 500 m3 respectively); revitalisation of drainage channels of around 2 400 metres ("m") long, greening and landscape works for open space and amenity area, as well as other associated works;
implementation of the environmental mitigation measures, environmental monitoring and audit ("EM&A") programme and construction supervision for the works mentioned in sub-paragraphs (a) to (c) above; and
detailed design for the expansion in development area (belonging to the works after Phase 1 Stage 1) after the Northern Metropolis Development Strategy was announced.
Project Office in Civil Engineering and Development Department:
North Development Office (Enquiry: 3547 1624)
Consultant:
AECOM - Halcrow Joint Venture
Arup - Binnies Joint Venture
Approved Project Estimate:
$27.1751 Billion
Related Website:
https://nm-santintech.hk/en/
Current Progress:
Construction commenced in December 2024
Contract:
Contract no. ND/2024/09
Scope:
The works mainly comprise:
site formation of lands (including site clearance) and ground investigation works;
land decontamination works;
archaeological survey;
diversion works of existing roads, cycle tracks, drainage, sewerage, water supply and utilities systems; and
implementation of environmental mitigation measures and environmental monitoring works for the works mentioned above.
Commencement Date:
31 December 2024
Completion Date:
2027
Contract Sum:
$359.23 Millions
Contractor:
CR15G-Tung Lee Joint Venture
Contract no. ND/2024/10
Scope:
The works mainly comprise:
site formation of lands (including site clearance) and ground investigation works;
construction of at-grade Road L27 connecting to Lok Ma Chau Road;
construction of associated works including footpaths, drainage (including construction of box culverts), sewerage, water mains, landscaping works and slope works; and
implementation of environmental mitigation measures and environmental monitoring works for the works mentioned above.
Commencement Date:
31 December 2024
Completion Date:
2028
Contract Sum:
$228.64 Millions
Contractor:
Kuly Construction & Engineering Company Limited
Contract no. ND/2025/01
Scope:
The works mainly comprise:
site formation of lands (including site clearance) and ground investigation works;
construction of at-grade roads (i.e. Roads L18, L19, L20 and L21) connecting to Lok Ma Chau Road, Castle Peak Road – Chau Tau and Kwu Tung Road;
construction of a sewage pumping station;
construction of associated works including cycle tracks, footpaths, drainage (including construction of box culverts), sewerage, water mains (including section of the DN1000 freshwater trunk main connecting the Sheung Shui Water Treatment Works and the proposed fresh water service reservoir in San Tin), landscaping and slope works; and
implementation of environment mitigat